When making estimates, it is necessary to base on technical requirements, construction conditions, construction methods in the explanation of construction drawings to apply accordingly.

Photo.
In the process of implementing the appraisal of construction projects, Mr. Cao Van Bich's unit (Quang Binh) encountered the following problems:
According to Circular No. 10/2019/TT-BXD dated December 26, 2019 of the Ministry of Construction promulgating construction norms, there is no estimated norm for the construction of "formwork into canals". Canals have rectangular cross-section, square shape, height h ≤ 50cm.
After the Circular No. 10/2019/TT-BXD of the Ministry of Construction took effect, Mr. Bich's unit appraised a number of infield canal works and applied the same norm as "long foundation formwork" with code brand name is AF.82511 for formwork to form canals. However, some investors and consulting units disagree with the appraisal results of his unit.
Mr. Bich asked, the construction of formwork to form an infield canal with dimensions B x H = 30 x 40cm and B x H = 40 x 40cm, thickness δ = 12cm applies similar norms: AF.81111 (base formwork, raft foundation, machine base; AF.81311 (straight wall formwork); AF.82511 (long foundation formwork) or AF.86211 (wall formwork)?
Currently, according to the provisions of Circular No. 10/2019/TT-BXD, the norm for transporting materials is only ≤ 60km. So, with the distance of transporting materials > 60km, how to calculate the material transportation fee? Is there any appraisal for urgent construction works?
The Ministry of Construction responded to this issue as follows:
Estimating norms for processing, erection and dismantling formwork for canal banks are specified in the Circular No. 10/2019/TT-BXD dated December 26, 2019 of the Ministry of Construction promulgating construction norms. , model number AF.81611 and model number AF.82611.
Therefore, when making cost estimates, it is necessary to base on technical requirements, construction conditions, construction methods in the explanation of construction drawings to apply accordingly.
The making of work construction estimates shall comply with the provisions of Article 12 of the Government's Decree No. 10/2021/ND-CP dated February 9, 2021 on management of construction investment costs.
The determination of the new cost estimate for the work shall comply with the provisions of Clause 1, Article 21 of Decree No. 10/2021/ND-CP.
The management of investment in the construction of emergency works shall comply with the provisions of Article 58 of the Government's Decree No. 15/2021/ND-CP of March 3, 2021 detailing a number of contents on project management. construction investment project.
According to Circular No. 10/2019/TT-BXD dated December 26, 2019 of the Ministry of Construction promulgating construction norms, there is no estimated norm for the construction of "formwork into canals". Canals have rectangular cross-section, square shape, height h ≤ 50cm.
After the Circular No. 10/2019/TT-BXD of the Ministry of Construction took effect, Mr. Bich's unit appraised a number of infield canal works and applied the same norm as "long foundation formwork" with code brand name is AF.82511 for formwork to form canals. However, some investors and consulting units disagree with the appraisal results of his unit.
Mr. Bich asked, the construction of formwork to form an infield canal with dimensions B x H = 30 x 40cm and B x H = 40 x 40cm, thickness δ = 12cm applies similar norms: AF.81111 (base formwork, raft foundation, machine base; AF.81311 (straight wall formwork); AF.82511 (long foundation formwork) or AF.86211 (wall formwork)?
Currently, according to the provisions of Circular No. 10/2019/TT-BXD, the norm for transporting materials is only ≤ 60km. So, with the distance of transporting materials > 60km, how to calculate the material transportation fee? Is there any appraisal for urgent construction works?
The Ministry of Construction responded to this issue as follows:
Estimating norms for processing, erection and dismantling formwork for canal banks are specified in the Circular No. 10/2019/TT-BXD dated December 26, 2019 of the Ministry of Construction promulgating construction norms. , model number AF.81611 and model number AF.82611.
Therefore, when making cost estimates, it is necessary to base on technical requirements, construction conditions, construction methods in the explanation of construction drawings to apply accordingly.
The making of work construction estimates shall comply with the provisions of Article 12 of the Government's Decree No. 10/2021/ND-CP dated February 9, 2021 on management of construction investment costs.
The determination of the new cost estimate for the work shall comply with the provisions of Clause 1, Article 21 of Decree No. 10/2021/ND-CP.
The management of investment in the construction of emergency works shall comply with the provisions of Article 58 of the Government's Decree No. 15/2021/ND-CP of March 3, 2021 detailing a number of contents on project management. construction investment project.